MFT Kolkwitz combines manual and automatic powder coating

Metall-Form-Technik in Kolkwitz previously packed parts for outside coating, transported them and prepared them again for assembly. In-house finishing was intended to reduce handling and simplify assembly scheduling.

Overhead tracks and metal components at MFT Kolkwitz
Project photograph from the original case study.

How the system works

Parallel booths, a loading area and transfer bridges were installed in a new hall. An automatic washer pretreats different metals. Operators use a manual booth for complex shapes and batches of one to 20. Larger runs go through the automatic booth with controlled friction-wheel drives. A vacuum evaporator treats process water, and several carrier positions in the oven accommodate different dwell times.

Project specifications

Workpiece envelope Up to 7 × 2.5 × 2.5 m
Carrier load Up to 1,000 kg
System JUMBO-COAT
Application Manual and automatic
Start of operation August 2017

Project results

The operator reported producing a three-section staircase in five days instead of up to three weeks. That figure covers the complete manufacturing and logistics process. QIB certification was still under review when the report appeared.

Project source

JOT, 2017/2018 project — “Prozesse, Qualität und Logistik auf einem neuen Niveau”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

Wenzel brings powder coating in-house for short lead times

Wenzel Schneidtechnik in Loßburg wanted to deliver finished parts and respond quickly to changing orders. Individual components and assemblies had widely varying shapes. The company extended its building and initially chose a mainly manual process.

How the system works

The wash booth, combined dry-off and curing oven, and powder booth stand in a row. A lifting station serves the loading area, and the Park-and-Drive system transfers carriers at right angles between stations. Steel is degreased and phosphated. The aluminium parts described were for indoor use. Wenzel later added an automatic spray frame. Energy planning also covered heating the washing process.

Project specifications

Workpiece envelope Up to 4 × 2 × 2.5 m
System JUMBO-COAT
Stations Wash booth, combined oven and powder booth
Materials Steel and aluminium
Retrofit Automatic spray frame

Project results

In September 2020 the operator reported lead times five working days shorter than with outsourced coating. Express orders could be completed in one working day under the conditions described.

Project source

BESSER LACKIEREN, 18 September 2020 — “Flexibler und schneller”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

HTM adds powder coating to its hot-dip galvanising services

HTM Feuerverzinkerei in Mühlhausen previously sent galvanised components to regional coaters. Packaging, transport and outside lead times all affected delivery. HTM converted an existing building to finish individual parts and a range of metals in-house.

How the system works

A blast booth with a movable platform complements washing. An electric transfer bridge takes suspended parts to the wash booth, combined dry-off and curing oven, and manual powder booth. The automatic washer can treat one wider or two narrow parts depending on loading. Pretreatment and rinsing sequences follow the substrate. Process chemicals are housed above the booths to save floor space.

Project specifications

Workpiece envelope Up to 6 × 1.5 × 2.5 m
Carrier load 1 t
Application Manual
Commissioned 6 June 2019
Additional equipment Blast booth with movable platform

Project results

The JUMBO-COAT system entered service on 6 June 2019. The report describes a new service that also supports the galvanising business. Its benefits were control over the process and a wider offering. The report does not quantify a throughput increase.

Project source

JOT 2/2020 — “Vom Feuerverzinken zum Pulverbeschichten”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

Wilsberg fits in-house powder coating into a 270 m² production area

At Wilsberg Metalltechnik in Bad Honnef, outsourcing meant packing, loading and transporting fabricated assemblies. Customers wanted shorter lead times. Bringing finishing into the sheet metal plant would reduce handling and help production respond faster.

Booths and overhead conveyor at Wilsberg
Project photograph from the original case study.

How the system works

Pretreatment, a combined dry-off and curing oven, and manual powder application stand side by side. The loading area doubles as a buffer, and a lifting station handles large parts. A travelling spray frame automatically pretreats work up to approximately 1.2 m wide. Operators clean large or complex parts with a lance. Process media circulate, and specialist contractors dispose of wastewater.

Project specifications

Workpiece envelope Up to 4 × 1.5 × 1 m
Maximum weight 1,000 kg
Footprint 270 m²
Application Manual
Production start June 2018

Project results

Two employees trained at MEEH before production started in June 2018. The operator reported greater throughput and less logistics work without assigning a percentage to either improvement. The account does not establish zero wastewater discharge.

Project source

MEEH — “Fertigungstiefe erweitert, Flexibilität erhöht”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

Maas + Roos brings powder coating for illuminated signs in-house

Sign and LED specialist Maas + Roos makes parts of different shapes and sizes in Hilpoltstein. Sending them out for coating took considerable handling, and customers expected durable, high-quality visible surfaces.

Yellow conveyor equipment and large lettering at Maas + Roos
Project photograph from the original case study.

How the system works

MEEH placed the process booths in parallel. An automatic spray frame pretreats aluminium with rinsing and passivation stages. An electric transfer bridge connects the washer, dry-off oven, curing oven and manual booth. Waste heat from curing supplies the dryer. Vacuum distillation treats process media, and carriers and a loading area accommodate varying batch sizes. Space was reserved for a second powder booth.

Project specifications

Carrier load Up to 1,000 kg
System JUMBO-COAT
Application Manual
Production start Early 2018
Expansion provision Second powder booth

Project results

Production started in early 2018. The report records around 160 orders a week in batches of one to 500. A second transfer bridge had already been added. The dimensions of individual sign letters are product examples, rather than line capacity limits.

Project source

JOT — “Pulverbeschichtet – Wirkungsvoller werben”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

ND Coatings powder coats pipework for shipbuilding at Meyer Werft

At the Meyer Werft shipyard in Papenburg, wet paint drying times tied up booths used for pipes and equipment parts. ND Coatings needed more throughput, good finish quality and lower solvent emissions across a varied part mix.

Pipework suspended in a coating booth at ND Coatings
Project photograph from the original case study.

How the system works

MEEH designed a roughly 70 m line linking blasting, cleaning, coating and curing. An overhead conveyor uses 25 carriers. After automatic blasting, parts are cleaned and masked. Operators apply powder manually because the geometries vary widely. Powder recovery, two adjacent curing ovens and buffer positions support different routes. Two carriers can be combined for exceptional heavy loads.

Project specifications

Standard workpieces Up to 5 × 1.5 × 2 m and 2 t
Special configuration Up to 4 t on combined carriers
Line length Approximately 70 m
Application Manual
Preparation Automatic blasting followed by cleaning

Project results

In the 2013 report the operator attributed a 70% increase in throughput and annual solvent savings of 60,000 kg to the changeover. These figures refer to that installation. ND Coatings operated the line at the Meyer Werft shipbuilding site.

Project source

JOT 2/2013 — “Bis zu 2 t schwere Kleinteile prozesssicher pulvern”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

Lackier-Müller combines manual and automatic powder coating for multiple metals

Corrosion protection specialist Lackier-Müller in Hofheim-Wallau needed capacity for more sizes and colours. A new production building provided space to handle larger workpieces in steel, aluminium and galvanised steel.

Process booths and orange conveyor equipment at Lackier-Müller
Project photograph from the original case study.

How the system works

MEEH integrated conveyors, pretreatment, drying and curing ovens, a manual booth and automatic application. An automatic washer cleans suitable smaller parts. Operators pretreat large components with a high-pressure lance in a walk-in wash booth. Rinse-water circuits, filters and an evaporator treat the media for reuse. Oven residence time is monitored according to material thickness, and return air and filtration are integrated into the building.

Project specifications

Workpiece envelope Up to 10 × 2.5 × 3 m
Maximum weight 4 t
System JUMBO-COAT
Application Manual and automatic
Materials Steel, aluminium and galvanised steel

Project results

The report identifies potential savings of at least 30% in energy and operating supplies. The comparison is insufficiently documented to treat this as a measured saving for other plants. The annual capacity quoted for the earlier equipment is separate from the new line’s throughput.

Project source

MEEH — “Lackier-Müller investiert in die Zukunft”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Modular coating systems · Coating system modules and buying guide · Discuss your project with MEEH

Henke fits automatic powder coating into 600 square metres

Henke wanted to finish its own sheet metal parts and reduce transport to outside coaters. Around 600 m² was available for a line handling different components and several colours each day.

Operator beside suspended parts and the red conveyor at Henke
Project photograph from the original case study.

How the system works

Indexed pretreatment is followed by drying, coating and curing. The compact conveyor uses carriers, controlled speeds and matched cycle times. The dry-off oven is integrated into the oven arrangement, and an evaporator treats process water.

Project specifications

Footprint Approximately 600 m²
Carrier length 3.5 m
Operation Automatic
Pretreatment Indexed with water treatment
Report year 2009

Project results

The 2009 report records around 100 carriers and more than 1,000 m² of coated surface per day for the part mix in use at that time. The installation illustrates how to integrate in-house finishing in a restricted space.

Project source

JOT 8/2009 — “Die kleine Welt des Blechs”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Automatic powder coating systems · Coating system modules and buying guide · Discuss your project with MEEH

Kramer adds powder coating for large and heavy components

Oberflächenzentrum Hegau-Bodensee, identified as Kramer in the report, wanted to complement its blasting and painting services. Heavy structures, small parts and varying batch sizes made a conventional continuous line for standard parts unsuitable.

Manual coating of suspended components at Kramer
Project photograph from the original case study.

How the system works

MEEH sized the pretreatment equipment and oven around the specified workpieces. A semi-automatic washer combines manual spot cleaning with an automatic spray frame. Separate media circuits serve different substrates. An electric transfer bridge connects stations and buffers, and a lifting and lowering station assists with heavy loads. A separate large spray booth handles wet paint jobs.

Project specifications

Workpiece envelope Up to 9.5 × 2.7 × 3.8 m
Maximum weight 6 t
System JUMBO-COAT
Pretreatment Semi-automatic
Additional process Wet spray painting

Project results

The 2008 installation extended the range of structures and small batches Kramer could finish. The source gives no general savings or throughput figure. For a comparable investment, the part dimensions, weight, pretreatment, oven and transport interfaces all need to be specified together.

Project source

BESSER LACKIEREN — “Sandstrahler wird Pulverbeschichter”. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

For large or heavy workpieces, use the powder coating system buying guide to specify hanging orientation, maximum load and handling requirements.

Modular coating systems · Coating system modules · Discuss your project with MEEH

Amazone powder coats agricultural machinery components in Samara

At the Amazone plant described in the report, small sheet metal parts and heavy assemblies had to meet the same finish requirements. The layout had to link loading, pretreatment, drying and powder application within the available floor space.

Process booths and conveyor equipment at Amazone
Project photograph from the original case study.

How the system works

MEEH designed a transfer area with longitudinal and transverse travel and buffer positions. Operators hang small parts by hand and use handling assistance for larger assemblies. The wash booth degreases, phosphates and rinses. The media are filtered and recirculated. Drying and curing times account for material thickness, and powder is applied manually in a walk-in booth.

Project specifications

Workpiece envelope Up to 9,200 × 2,000 × 2,500 mm
Maximum weight 2,000 kg
Footprint Approximately 30 × 22 m
System JUMBO-COAT
Application Manual

Project results

The 2017 report describes successful start-up and employee training in Wimsheim. It documents the installation at that time and makes no claim about the present status or ownership of the site.

Project source

Project reprint, 21 April 2017 — “Bleche für Landmaschinen in hoher Qualität pulverbeschichten”. The figures describe the installation and operating conditions documented in the report.