MFT Kolkwitz combines manual and automatic powder coating

Metall-Form-Technik in Kolkwitz previously packed parts for outside coating, transported them and prepared them again for assembly. In-house finishing was intended to reduce handling and simplify assembly scheduling.

Overhead tracks and metal components at MFT Kolkwitz
Project photograph from the original case study.

How the system works

Parallel booths, a loading area and transfer bridges were installed in a new hall. An automatic washer pretreats different metals. Operators use a manual booth for complex shapes and batches of one to 20. Larger runs go through the automatic booth with controlled friction-wheel drives. A vacuum evaporator treats process water, and several carrier positions in the oven accommodate different dwell times.

Project specifications

Workpiece envelope Up to 7 × 2.5 × 2.5 m
Carrier load Up to 1,000 kg
System JUMBO-COAT
Application Manual and automatic
Start of operation August 2017

Project results

The operator reported producing a three-section staircase in five days instead of up to three weeks. That figure covers the complete manufacturing and logistics process. QIB certification was still under review when the report appeared.

Project source

JOT, 2017/2018 project — “Prozesse, Qualität und Logistik auf einem neuen Niveau”. The figures describe the installation and operating conditions documented in the report.