Wilsberg fits in-house powder coating into a 270 m² production area

At Wilsberg Metalltechnik in Bad Honnef, outsourcing meant packing, loading and transporting fabricated assemblies. Customers wanted shorter lead times. Bringing finishing into the sheet metal plant would reduce handling and help production respond faster.

Booths and overhead conveyor at Wilsberg
Project photograph from the original case study.

How the system works

Pretreatment, a combined dry-off and curing oven, and manual powder application stand side by side. The loading area doubles as a buffer, and a lifting station handles large parts. A travelling spray frame automatically pretreats work up to approximately 1.2 m wide. Operators clean large or complex parts with a lance. Process media circulate, and specialist contractors dispose of wastewater.

Project specifications

Workpiece envelope Up to 4 × 1.5 × 1 m
Maximum weight 1,000 kg
Footprint 270 m²
Application Manual
Production start June 2018

Project results

Two employees trained at MEEH before production started in June 2018. The operator reported greater throughput and less logistics work without assigning a percentage to either improvement. The account does not establish zero wastewater discharge.

Project source

MEEH — “Fertigungstiefe erweitert, Flexibilität erhöht”. The figures describe the installation and operating conditions documented in the report.