ND Coatings powder coats pipework for shipbuilding at Meyer Werft

At the Meyer Werft shipyard in Papenburg, wet paint drying times tied up booths used for pipes and equipment parts. ND Coatings needed more throughput, good finish quality and lower solvent emissions across a varied part mix.

Pipework suspended in a coating booth at ND Coatings
Project photograph from the original case study.

How the system works

MEEH designed a roughly 70 m line linking blasting, cleaning, coating and curing. An overhead conveyor uses 25 carriers. After automatic blasting, parts are cleaned and masked. Operators apply powder manually because the geometries vary widely. Powder recovery, two adjacent curing ovens and buffer positions support different routes. Two carriers can be combined for exceptional heavy loads.

Project specifications

Standard workpieces Up to 5 × 1.5 × 2 m and 2 t
Special configuration Up to 4 t on combined carriers
Line length Approximately 70 m
Application Manual
Preparation Automatic blasting followed by cleaning

Project results

In the 2013 report the operator attributed a 70% increase in throughput and annual solvent savings of 60,000 kg to the changeover. These figures refer to that installation. ND Coatings operated the line at the Meyer Werft shipbuilding site.

Project source

JOT 2/2013 — “Bis zu 2 t schwere Kleinteile prozesssicher pulvern”. The figures describe the installation and operating conditions documented in the report.