The project required two new buildings. Construction started in April 2023. Once the floor could take installation traffic in October, MEEH began assembly. The first coated roof brackets came off the line in February 2024.

Project specifications

Construction began April 2023
Assembly began October 2023
First coated brackets February 2024
Oven fuels Gas or oil

Energy management

Parts pass through compact pretreatment and into a dry-off oven heated by exhaust air from the curing oven, which can run on gas or oil. Hot coated parts then pass through a heat recovery zone. Energy recovered there is returned to the curing oven.

The controls detect empty conveyors. When no more parts are approaching, they stop the automatic booth fans and reduce other loads. As soon as parts are loaded again, the controls wake the line in time for their arrival.

Project source

BESSER LACKIEREN, 26 May 2024, issue 9/2024. The figures describe the installation and operating conditions documented in the report.

Planning a coating system

Automatic powder coating systems · Coating system modules and buying guide · Discuss your project with MEEH

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *