Dresel automates powder coating for steel, aluminium and galvanised parts
Beschichtungszentrum Dresel in Rheinfelden already used a JUMBO-COAT line for large and heavy work. Growing demand called for a second system for series orders. An adjoining former warehouse and beverage hall was available. MEEH had to coordinate pretreatment, ovens, conveyor, booth and application equipment in limited space. After comparing concepts, Dresel chose modular FLEX-i-COAT, installed in 2019.

How the system works
A lifting station loads the power-and-free conveyor. Aluminium follows a dedicated degreasing, pickling and passivation route. A separate line degreases and iron-phosphates steel and galvanised work. After drying, an automatic booth applies powder with recovery, and parts pass into the curing oven. Station cycles were matched to process times.
An evaporator treats water to support the zero-effluent operation described in the report. Chemicals are dosed automatically, and the in-house laboratory regularly checked process values. The dry-off oven is integrated into the oven arrangement. In winter, heat from the cooling zone can heat a neighbouring warehouse. The report does not quantify an energy saving.
Project specifications
| Operator | Beschichtungszentrum Dresel, Rheinfelden |
|---|---|
| System | MEEH FLEX-i-COAT |
| Conveyor | Power-and-free with lifting station |
| Workpiece weight on new line | Up to 300 kg |
| Carrier length | 3 m |
| System dimensions | 23 × 18.8 × 5.2 m plus 18 m for workpiece transfer |
| Pretreatment | Separate lines for aluminium and for steel and galvanised parts |
| Tracking | Carrier QR codes and recorded process parameters |
Traceability and results
QR codes on the carriers identify the order and settings for colour, film thickness, rinsing, passivation, curing time and temperature. The display shows carrier positions. Recorded target and actual values make individual orders traceable.
The 2020 accounts describe five employees processing about 60 carriers per shift, with numerous colour changes. Orders typically took two to three days and sometimes less. Series work on the new line freed the existing JUMBO-COAT system for large parts and urgent orders. These are historical operator figures for that part mix.
Project source
BESSER LACKIEREN, 5 June 2020, p. 3, JOT 7–8/2020 and the MEEH project reprint. The figures describe the installation and operating conditions documented in the report.