Planning a powder coating system: a buyer’s checklist

Start with the parts you need to coat, the production schedule and the building where the line will run. Booth dimensions alone tell a supplier little about how the system will work. Use these seven steps to prepare a specification that suppliers can quote against.

1. Describe the parts and the finish

List typical parts as well as the longest, widest, tallest and heaviest items. These may be different parts. Record the material, wall thickness, hanging orientation and surface condition on arrival. Describe where the product will be used and what the coating must withstand. Choose samples that represent the range of work.

2. Specify throughput, batch sizes and changeovers

Record quantities per shift, batch sizes, shift patterns and expected changes in demand. How often will operators change colours or part types? Who will load and unload the line? These details help determine whether a modular batch system or an automatic continuous line suits your production. There is no single volume threshold for that decision.

3. Follow the workpiece through the whole process

Trace each part from loading through pretreatment, drying, powder application and curing to unloading. Specify how it moves between stations. The substrate, incoming surface condition and required finish determine which process modules you need alongside the powder booth.

4. Check the building and utilities

Mark columns, doors, clear height, existing equipment and transport routes on a floor plan. Trace the largest part through loading and unloading. Allow space for buffers, operators, cleaning and maintenance. Identify available utility connections and the area you want to reserve for expansion.

5. Separate investment costs from operating costs

  • Equipment: process stations, workpiece capacity, conveyor design, automation and control interfaces.
  • Installation: building work, utility connections and the installation and commissioning services included in the quotation.
  • Operation: production hours, labour, energy, process materials, cleaning, maintenance and wear parts.
  • Future changes: new parts, higher volumes and additional stations.

Use the same production programme for each comparison. Suppliers need these operating assumptions to produce a project-specific quotation.

6. Compare quotations against the same specification

Check that each supplier has allowed for the same workpieces, quantities and finish requirements. Ask who supplies each connection, which work your team must carry out and how responsibilities are divided at the interfaces. Agree on commissioning, operator training and maintenance and support. Compare performance figures alongside the conditions under which they apply.

7. Resolve open process questions with sample parts

If pretreatment, access to recessed surfaces or finish quality is uncertain, arrange coating trials at MEEH’s technical centre. Agree on representative samples, the objective and how the finish will be assessed. A trial establishes results for those conditions. Material flow, throughput and the production layout still need their own assessment.

What to include in your first enquiry

  • Typical and maximum dimensions, weights, materials and hanging method
  • Incoming surface condition, end use and required finish
  • Quantities, batch sizes, shifts, part mix and colour changes
  • Floor plan, transport routes, utilities and existing equipment
  • Automation requirements, operating priorities and expansion plans

See how these choices played out in practice: large steelwork at Huppertz, restricted floor space at Schachtel and heat recovery at Otto Lehmann.

Have your hall and workpiece dimensions ready? Create an initial layout in the coating system configurator or discuss your specification with MEEH.